Regarding you had completed resource loading and been authorized of your baseline.1.Fix Duration &Units2.Fix Duration &Units/time3.Fix units4.Fix Units/timeThen what percentage type you usually adopt.1.Duration2.Physical 3.Unit.Actually, I am not very sure how it engage this two elements to make it work well.Maybe you guy can provide your well experience here.Thanks!
Hi Louis
If your schedule if resource loaded i suggest that you use Physical percentage type. The advantage is that you can spit the remaining duration and the % completion. This is particularly useful when you apply Earned Value Techniques. The disadvantage is that you have to update every single activity and apply remaining duration and % complete.
Johannes