I seek help from the forum members on the following:
When I schedule P6, the non progressed activities acquire the data date as their Planned Start Date and the Original Duration also changes. I guess some setting may be wrtong, but I couldn't locate the wrong setting. Can someone please guide me?
Thanks in advance.