Activity driving, links problem
Need Hels guys..
- Read more about Activity driving, links problem
- 9 comments
- Log in or register to post comments
General planning comments and questions.
Need Hels guys..
Hi all,
Hi all,
May i request you time to get some explanation regarding the design and the procurement in a major puming statiion. My understanding is like as follows,
1. For the design works, the main contractor will make the Process Flow Diagram(PFD) and the P&ID will follow.
2. The vendor will prepare the design of the major equipments(like pumps, transformers etc) based on the contract specification provided by the main contractor.
In my department there are many kpi's for maintenace planning such as schedule compliance , Planning and Scheduling Effectiveness (Actual versus Planned completion) ,emergancy man hours & rework man-hours.
Dear all,
Hello,
I am involved in a MEP construction project for a high rise project in UAE, I am missing the productivity norms/standard manhours for electrical activities in order to monitor and compare prcisely the planned and actual performance of the works done. If any body have some information or experience related to electrical works and help me in this matter I shall be very thankful.
Regards
/Mohsin
I am a new planning engineer with just a year of experience. I need to prepare the construction schedule for a chemical plant. I have the scope of work discipline wise. I am not able to determine the duration of each of the activities, example excavation. I know what the volume of work is but since I am not able to determine the rate of work, I am not able to determine the duration of activity. This is very critical as I need to determine an optimistic time frame for the construction works by rolling up all the individual activities.
The major works are
Hi Everyone,
I am new planner who's being asigned to build a draft programme for Earthworks. Please can any one help me out with a basic activities that is required for an earthworks programme in rail or kindly advice me on how to go about it.
Many thanks.
Ken.
Hi all,
I am new to planning feild, and need some help regarding the best combination to use in a road project
The exisiting schedule at my site have all the activities listed "% complete" types as "duration" for all the activities.
As its an expressway project, people are more concerened about the major commodities they achieve monthly and % progress tracking is done based on that in excel files. i hope with all the big road projects its like that.
Mostly activities are happening not as planned due to terrain restrictions and all those.
Please i need somone to help me with the rate for the following:
1. Standing seam roofing sheet.
2.Steel.
3.Glaxing Curtain wall.
4.Aluminum Composite Panel ACP Cladding.
4.Sealant
5.Aluminium Frame.
How to make a report to know which activities has a constrain in the whole program ??