Weightage allotment to activities

Here we are following some Common Sence rule foe giving weightage to activity

Consider Boiler:

Boiler-100%

1) Engg-10%.

2) Procurement-50%

3) Construction-40%

Now Consider 1) Engg-10%

                      a) Civil-1%

                      b) Mechanical-7%

Forum Sponsor

Top Posters

Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts

LNG Terminal Project

S
Sunil Babu 👤 Member for 15 years 7 months

Daer All,

I am awaiting the expert opinion regarding the construction of a LNG Terminal project.

Major activities of the project includes Offshore dredging works, Pipe laying works, Tranfering gas to Onshore , Processing gas at onshore and to the distribution. What are the methodology for this project and what are the risk elements involved.

What are the major civil and mechanical works involved . Also equipment mobilization requirements ..

Your views will be highly appreciated.

With Best Regards,

Sunil.

Forum Sponsor

Top Posters

Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts

Store period performance

Dear Experts ,

When I checked our contractor's weekly and Monthly report , I found that each weekly and monthly period showing diffrent actual figures for the same month . I guess promavera just distribute the actuals over the period every time when it gets updated

My first question is - is this an reasonable reson to say that  data comes from P6 software ? or we have to do it manually to make sence ?

Second- Contrator is reluctant to use the option "Store period performance"  

your view please ?

Janaka

 

Forum Sponsor

Top Posters

Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts

Forum Sponsor

Top Posters

Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts

Forum Sponsor

Top Posters

Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts

Car sale showroom - split foundation and Steel structure

E
Engy Sarhan 👤 Member for 11 years 7 months

Hi there,

 

I am wondering if anyone could help me with a sequence and possible durations to put together a schedule for a carsale showroom, it should have a split foundation and a steel structure superstruction, single story building with an area of 3000 sqm.

Any help will be appreciated.

Forum Sponsor

Top Posters

Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts

Subcontractor's Schedule Imported but no Actual Earnings

Hello,

I have received and imported an update from a subcontractor which has actual progress for activities.  My problem is that their actual material and labor resources are all zero's.  We have both shared screen shots and in his schedule he has values for the actual material and labor.  I do not have any of those actual resource values that he is showing me.  I know that he is sending me the correct file and my resourece settings are as follows.

Labor Resource

Forum Sponsor

Top Posters

Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts

Forum Sponsor

Top Posters

Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts

Forum Sponsor

Top Posters

Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts

New Website with PM Blogs and Exercises in Critical Path Drag and Drag Cost

I have just launched this new website named after my first book and the Total Project Control (TPC) methodology which emphasizes the importance of expected monetary value (or, if you prefer, ROI) as a key project and program management metric.

Forum Sponsor

Top Posters

Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts