Actual Start Woks before effective date

Dear All Master Primavera<

I am Prastya,  I am is newbie to used primavera P6 in my project and still to learn and explore for this software,

I have problem during making the schedule, because in my project now already start work but the owner not state the effective date yet

Actually at site already work, but I must to insert this actual date to schedule.

 

So How to setting this problem ? (like this picture)

Forum Sponsor

Top Posters

pinoyplanner
0 posts
James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts
Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts

Forum Sponsor

Top Posters

pinoyplanner
0 posts
James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts
Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts

Forum Sponsor

Top Posters

pinoyplanner
0 posts
James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts
Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts

Forum Sponsor

Top Posters

pinoyplanner
0 posts
James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts
Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts

Forum Sponsor

Top Posters

pinoyplanner
0 posts
James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts
Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts

How to Edit Relationship Line Size/Thickness

R
Richard A 👤 Member for 11 years 11 months

Hello Folks,

I need your help in this. 

While I know that the Relationship line colours (black and red) cannot be changed in P6, I need help in changing the relationship line size/thickness. Especially the red one for Critical Path. I have searched  through the menus and option but with no luck. I noticed the lines are quite fine when in activity page, but once I get into the print preview, the Critical Path Relationship lines gets uncomfortably bigger and shows as such when printed. Below is an example of what I mean.

Regards

Forum Sponsor

Top Posters

pinoyplanner
0 posts
James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts
Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts

Forum Sponsor

Top Posters

pinoyplanner
0 posts
James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts
Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts

P6, Resource Assignment would not import for repeated resource

E
edul mar 👤 Member for 8 years 11 months

I try to import Resource Assignment from Excel to P6, 

I have several activities that have repeated resource. When I import the excel file to update my P6 project, only the first resource iis imported while other repeated resource will be ignore. Is there any method to make P6 import all repeated resources without ignoring the repeated resource?

I cannot create the repeated resource as a new resource because I need the collect the repeated resources data later as one lumpsump data.

Forum Sponsor

Top Posters

pinoyplanner
0 posts
James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts
Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts

Export Schedule % and Actual % progress values from P6 to excel

S
susan ann 👤 Member for 12 years 6 months

Can anyone please advise how to export Schedule % and Actual%  values from P6 to excel ? This is mainly to generate the planned and actual S curves for the project.And I need its cumulative too... Any amout of help is appreciated. Thanks in advance.

Forum Sponsor

Top Posters

pinoyplanner
0 posts
James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts
Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts

Forum Sponsor

Top Posters

pinoyplanner
0 posts
James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts
Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts