P6, Resource Assignment would not import for repeated resource

E
edul mar 👤 Member for 8 years 10 months

I try to import Resource Assignment from Excel to P6, 

I have several activities that have repeated resource. When I import the excel file to update my P6 project, only the first resource iis imported while other repeated resource will be ignore. Is there any method to make P6 import all repeated resources without ignoring the repeated resource?

I cannot create the repeated resource as a new resource because I need the collect the repeated resources data later as one lumpsump data.

Z
Zoltan Palffy 👤 Member for 16 years 10 months

go to the projects directory 

make sure that your project is highlighted

Click on the Resources tab

lower right under Resource Assignmets make sure that the box that says Resources can be assigned to the smae activity more than once IS CHECKED.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts