Changing the Resource Type

K
Kannan CP 👤 Member for 17 years 11 months

In a Programme, all the equipments are assigned as Labor type, by mistake. While trying to change the type in the Resource Pool, it is showing the message as Not Possible to Change. Tried the Global Change and unsuccessful.

 

Any solution to rectify it.

Regards

Kannan

Z
Zoltan Palffy 👤 Member for 16 years 10 months

copy existing resource info to excel 

create a new resource

delete old resource

assign new resource

export new resource and budgtes to excel

populate new resource budgets with info form old resource budgets

import new resoruce budgets