Dear All,
I make a schedule. Done resource loading. Add labour resource to the each activity.
Now I am trying to make monthly manpower histogram.
When I open Resource Assignments windows it's showing the budgeted units allocated to my schedule according to the time scale i set. (Let's suppose I set Quarter/Monthly). This window is showing me the budgeted Units of labour per month. But I need the Manpower per month and want to extract it to excel. So I can make manpower histogram.
How can I get the manpower from budgeted Units