Is there a way to enter a day rate rather than an hourly rate in Primavera?
Day Rate for Resources
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
in the resource the default units/time is day
Set the Unit of Time in Day for Unit Format and Duration Format in the User Preferences under Time Units Tab