Missing project codes - feels like deja vu
I googled this and searched this site. Question: I go and create "project codes". Then I try to add it as a column and it is either missing or if able to pull up it will not let me add the values from a pull down menu like normal codes. I believe I have encounted issues with project codes before but cannot remember how to resolve this issue. Any advise. I should be able to just add a code to a dictionary, add values, pull up those values. Does not work that way, what am I missing? I made it unique to avoid the dupe name issue.