Primavera (EPPM) how to filter activities with particular resource assigned

C
Chary Chary 👤 Member for 10 years 1 month

Dear all,

I am just trying to find a way to do what is quite simply done in Ms Project: to filter activities, which have a particular resource assigned to them.

The only way I found is to go to assignments and to create a filter, which filters assignments based on a project.

Is there a way to do it out of Activities?

Z
Zoltan Palffy 👤 Member for 16 years 10 months

yes 

filter 

where resource name equals what ever the resource name is 

S
Santosh Bhat 👤 Member for 21 years 1 month

Look in the Reource Assignments view rather than in the Activities View.