Planning activities in "Hours" with MSP

Greetings,

I was using P6 on my previous Project. I have a a 4 day shutdown plan to develope and I need to plan the start and finish in hours for the same.

I just cant find aany option with MSP 2007, like Primavera P6 where i can enter the planned start or the actual start in hours along with the date.

I will be working on a 12 hours per day calendar during the 4 day shutdown and i need to plan the activities in hours. and then update the actuals in hours too.

Please advise.

Thanking You,

Abdullah.  

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts

MSP 2010 wont let me baseline project

Hi All,

MSP 2010 will not let me set the entire project as a baseline. Ive tried it by selecting the entire project check box as well as highlighting all tasks then checking 'selected tasks'. It will let me assign a baseline if I select only a few tasks but thats it. My plan has 2500 tasks. I tired selecting 500 tasks but it wouldn't do this either.

Any ideas greatly appreciated as you can imagine this is causing me some frustration.

Cheers

Steve

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts

Total slack

Good evening guys,

I have got one question i have scheduled one project in picrosoft project.

start date is : 18.07.2011

End date is 30.08.2011

Relation :FS

i have entered status date as 28.07.2011 and i dint updated any tasks, then i enetred F9 to caleculate mannually , i am not able to see any negative slack of 10 days (or delay of 10 days since i dint started any work) 

if any one has answer please let me know. thanks in advance please note i have tried with must finish contraint too but the resilt is zero

 

 

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts

move complex set of tasks/subtasks without losing the structured numbering

I need to copy/move a complext set of tasks & sub task (many levels) under newly added task without losing the relative structured numbering.  Can't find it in the manuals.

 

I have Proj 2007.   I have been given a 1,000+ row plan, and need to move various chunks of the long plan into (under) new phase/task/subtasks.  When I expand all levels I had hoped to select all and paste them in to a blank set of rows, but I can't get the relative numbeing to be maintained.  My alternative is to print out the whole 1000 lines

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts

How can I create a "Custom Work Field"

I would like to implement custom fields which display a work value, for example "20 d". The fields can be either calculated (e.g. the work of a specific resource group), or entered (e.g. an initial estimate of work, which should not be entered in the standard "Work" field yet).

How can I create a field which displays the values including the units (e.g. "d" or "hrs").

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts

Cash Flows for Subprojects/ Grouping Projects by Project Managers

Hi All,

I am very new to MSP. I have created master project linking sub projects but when i go for the cash flow resports it gives cash flow for all organisation not for indivisual departements of organisation

GROUP (Master Schedule/Project)

CIVIL( Sub Project)

INFRASTRUCTURE( Sub Project)

ENVIRONMENTAL( Sub Project)

WATER RESOURCES ( Sub Project)

 

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts

MS project 2003 Duration and Finish does not reconcile

I have a strange problem, I want change my clander from 8 hrs to 9 hrs. Before doing it on the project i experimented

Created a new project put an activity

Name              Duration           Start              Finish

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts

Driving calendars

Everyone,

 

I currently have a 14 day (7 day calendar-no BH holidays) running through Christmas. It is the last path on the network, barring a finish milestone for 'planned completion'. which is its successor. This milestone has a 5 day claendar. As the previpous 14 day task is showing a finish of 30/12/11 the milesone finishes at the same (not honouring its calendar). If it was to honour its calendar, it should read 09/01/12. Can anyone tell me how to make the succeeding task calendar be the driver in MSP 2007 Pro.

 

Thanks Stuart

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts