How can i delay my project one day

hi all,

i changed a working day to non-working day, so i need my project to respect that change to all next tasks after that day, but project made over-allocations

can anyone help me

K
Khaja Sharief 👤 Member for 17 years 10 months

Dear Ahmed,

    I suggest you to check whether in the project information you have kept finish date of the project. If this is done and since end date is fixed and now you change working day to non working day then logically the end date should be pushed to the next working day. Since the finish date was fixed, the project would suggest for over allocation. 

K
Kris Harry 👤 Member for 21 years 9 months

Please try rescheduling with "link tasks" after selecting all tasks.

Kris

A
arif khan 👤 Member for 15 years

Hi Ahmed,

Just as you said, I created a Task A that starts on 1/Sep/2011 with a "Fixed Duration" of 60 days. Project automatically created the task as "Manually Schedule". I changed it to "Automatically Schedule". In the Standard Calendar (the one this project depends upon), I marked 1/Sep/2011 as a Nonworking day. Automatically Task A start date changed to 2/Sep/2011 and the Finish date also moved by one day keeping the duration same.

Arif

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts