No

Schedule % Complete

K
kumar s 👤 Member for 16 years 4 months

Hello All,

Please guide me as i am new to MSP...

1) I have Prepared the schedule and set the baseline and updated the schedule for 1 week.

Now i want to show the Schedule % Complete Column Against the Actual % Complete.But i cannot find the Schedule % Column.Where i can get it.

2) For Showing the Actual % complete which of the % complete can be used as there are 3 types (% complete,Work % complete,Physical % Complete).

3) Is it neccesary to add resources to your project to monitor the Project or it can be done without resource assignment also.

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts

How to remove the indent and outdent function in MSP

K
kumar s 👤 Member for 16 years 4 months

Dear All,

 

Is there a way to remove the outdent option while taking the print.My proejct manager want to show less gap in the task name column which is appearing because of the outdent option.I know there is option in P6 to remove this while we are taking the print..

please guide if this can be done in MSP also

 

thanks

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts

Cumulative baseline work

B
Bogdan Dinu 👤 Member for 13 years 9 months

Hi,

I am new at this forum and I hope that you guys can help me out.

I want to creata a column, custom field in MSP 2010 that contains baseline work cumulative from the start of the project all the way to the current status date. 

Can not find this funcation anywere, does it exist?

 

Kind regards

Bogdan D

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts

Working with Microsoft Windows 8

Hi Guys,

The Ten Six team has been running tests on the latest pre-release copy of Windows 8 specifically to see how well it supports our primary tools of specialization; namely Microsoft Project, Deltek Cobra and Primavera P6. http://ow.ly/d9GQq

I hope this helps you better understand what's coming down the pike.

Emily

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts

MS Project 2007 prof file error.

Just recently I have produced updated programmes with no problem. Now when I save the current programme with a different name (i.e. Rev 09, save as Rev 10). When I close MSP and try and open the Rev 10 it says there is an error and cannot open. I have triied saving the file in different locations and opening again, to no avail. Why does Rev 09 open? But Rev 10 with the exact same information report an error?

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts

HOW TO ASSIGN 1 CALENDAR FOR THE SAME PROJECT

K
kumar s 👤 Member for 16 years 4 months

Dear All,

 

I have kept the standard default calendar as 8hrs and 5 days wroking for the project.However for some activites i need to assign a calnedar of 24hrs working per day and 7 days a week.Can i do this and how to do it.I found it very easy in P6 to assign diff calendar.

Please reply back..

thanks in advance

 

Regards,

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts