Hello All,
Please guide me as i am new to MSP...
1) I have Prepared the schedule and set the baseline and updated the schedule for 1 week.
Now i want to show the Schedule % Complete Column Against the Actual % Complete.But i cannot find the Schedule % Column.Where i can get it.
2) For Showing the Actual % complete which of the % complete can be used as there are 3 types (% complete,Work % complete,Physical % Complete).
3) Is it neccesary to add resources to your project to monitor the Project or it can be done without resource assignment also.
Thanks in advance
Kumar S
Hello Sir,
thanks for ur reply.
Ok Then is there a way to get the Planned % complete week wise for my project from MSP.
I have to show the week wise planned % of my project to my cleint one week before i start to monitor the project...
In P6 I used to change the data date(Week wise) and get the planned % complete for that week.So is there anything like this which can be done in MSP also.
The % Completes that MSP has are:
For any other you will need to enter a formulae ina custom column.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
www.eh.com.au
www.eastwoodharris.com
www.primavera.com.au - a Primavera scheduling software resources site