Dear All,
I have recently upgraded from MSP 2003 TO 2007.In the Date format option I am trying to select the format of
Mon 20/2/12,but i cannot find that option there wha is the reason...
Please guide me
Dear All,
I have recently upgraded from MSP 2003 TO 2007.In the Date format option I am trying to select the format of
Mon 20/2/12,but i cannot find that option there wha is the reason...
Please guide me
thank you
Hello Kumar,
MS Project takes its date formats from MS Windows; for instance, if MS Windows standard date format is MM/DD/YYYY, MS Project will display todays' date as "09/06/2012"; if the format is DD/MM/YYYY, the result is "06/09/2012"
Alexandre