Dear All,
I have kept the standard default calendar as 8hrs and 5 days wroking for the project.However for some activites i need to assign a calnedar of 24hrs working per day and 7 days a week.Can i do this and how to do it.I found it very easy in P6 to assign diff calendar.
Please reply back..
thanks in advance
Regards,
Thank you Alexandre
Kumar,
1. define a new calendar
2. double-click the task name you want to assign the calendar to, you will open the "task Information" dialog
3. display the "Advanced" tab, then select the new calendar in the "Calendar" drop-down list
4. if you have assigned resources to the task, and you want the task calendar to gain over the resource calendar, check the adjadent check box