Preparation and Evaluation of Acceleration Schedule
Hi All, Contractor agreed to submit acceleration schedule.What I understand about the acceleration is if the project delay is 8 months, and if Contractor agreed to accelerate in 4 months, they need to compress the schedule from 8 months to 4 months.If the Contractor agreed to submit acceleration, would it be from the current updated schedule and compress the schedule?How to evaluate acceleration programme and costs that are associated with it? Many Thanks!