Impacted as Planned on Recovery Schedule or BL Programme using P6

Member for

19 years 10 months

Hi Dimple - welcome to planning planet.

It depends when your events start.

If the problems occurred before the revised programme then you should start the analysis from the baseline programme.

If not then you can use the revised programme.

I am assuming that you will be using this for some sort of negotiation because your selected method will not pass investigation by a tribunal.

Best regards

Mike T.