Delay Analysis Method
Dear All,
I am preparing a EOT claim schedule(only time analysis, no prolongation cost). I am using the method Impacted As planned in order to identify the entitlement. The phases of work is as follows;
1. Submission of concept design: 30 days
2. Approval of concept design: 15 days
3. Submission of detailed ddesign: 50 days
4. Approval of detailed design: 15 days
5. Tender documents submission: 30 days