Is the delay excusable?
Our contractor is building a office block. The structural steel was scheduled to arrive on site in the 12th week, but the nominated supplier delivered it two weeks late.
The contractor missed the milestone for completing the steel frame, pushing back mechanical, electrical, cladding trades. I am tasked to write a simple report to answer the Engineers challenge of "Is this delay excusable (entitling the contractor to an EOT), or is it non‑excusable (i.e. our contractor’s risk)?
- Read more about Is the delay excusable?
- 5 comments
- Log in or register to post comments