How to remove suffixes from dates and display both dates for milestones in Primavera P6

If you came into Primavera P6 from a Microsoft Project background, you would have noticed that actual dates have the suffix “A” appended to them, and constrained dates also have an asterisk appended. And milestones have a blank date field depending on the type of milestone.

In this YouTube video, I will show you a trick you can use to

How to show Primavera P6 dates in month-year (mmm-yy) format

The date formats available in Primavera P6 are very limited and to best of my knowledge, you cannot get the mmm-yy (month-year) format straight out of the box. You might want to display dates in mmm-yy if you don't want to show exact dates in issued schedules.

This P6 video outlines a workaround using UDF that can be used to achieve mmm-yy date format.

2 Ways to Show Ordinal Dates instead of Calendar Dates in Primavera P6 Schedule

In this tutorial, I will show you 2 methods of displaying ordinal dates in a Primavera P6 schedule, the first method uses Microsoft Excel and the second uses Global Change facility in P6. Ordinal dates schedules are usually required when a project does not have a defined calendar start date.

How to use Activity Duration Type in Primavera P6

(If the image is too big, you can read the original article at this link : https://doduykhuong.com/2018/03/25/how-to-use-activity-duration-type-in-primavera-p6/ )

In Primavera P6, when we assign resource to activity there is a equation:

Original Duration x Units/Time = Total Units

(          10 days        x 8 hours/day = 80 hours         )

What is the difference between Activity type: Task Dependent and Resource Dependent in Primavera P6

In Primavera P6, there are 2 popular activity type: Task Dependent and Resource Dependent.

So what is the difference?

By choosing Task Dependent or Resource Dependent, P6 will choose what calendar it will use for the activity:

  • Choose Task Dependent: P6 use Activity calendar for the activity
  • Choose Resource Dependent: P6 use Resource calendar for the activity

Then it will affect the Original Duration and Finish Date of the activity.

We have Activity A with attribute as below: