Determine the longest path of a resource leveled schedule in P6

Unfortunately when it comes to resources and resource leveling, P6 model is absolute. P6 doesn’t calculate the float correctly and the longest path will not be accurate since the late and early dates will not change after leveling.

Primavera P6 doesn’t take in consideration the new dates after the leveling in calculating the total float or the longest path, to illustrate further if we have a project consists of three activities A,B & C and they all share the same resource and each activity 5 days duration and the project completion after 15 days.

Beyond the Critical Path - the Need for Logic Analysis of Project Schedules

Full Article / Information

Beyond the Critical Path - the Need for Logic Analysis of Project Schedules

By Thomas Boyle, PE, PSP, PMP

This entry is intended to review the use of the Multiple Float-Path calculation option in Primavera Project Planner (P6) and to offer a brief example of its use compared to BPC Logic Filter.