Planning Engineer, Tekfen Construction and Installation Co., Inc., AGIP KCO Gas Field Development Kashagan Main Works

START Date
END Date
Experience Hours (Planning & Scheduling)
4000
Experience Hours (Cost Management)
2000
Experience Hours (Forensic Analysis)
1500

Client: Agip KCO (Gama – Tekfen J.V.), Kazakhstan – http://www.agipkco.com

Kashagan Main Works Project, Trench-I& II (KMW, The world’s fifth largest oil field)

Project controls/planning activities of 730.374 WDI pipe fabrication& 234.861 WDI field erection (total 965.235 WDI welding), 225.771 m2 painting and 78.561 m2 insulation. Support to construction technical office for establishing & implementation of piping database for progress follow-up and reporting.

Final Project Value: US$ 718.698.634