Progress Tracking DB Design

Planning Engineer, Tekfen Construction and Installation Co., AGIP KCO Gas Field Development Kashagan Power Plant Project

START Date
END Date
Experience Hours (Planning & Scheduling)
5500
Experience Hours (Cost Management)
5500
Experience Hours (Forensic Analysis)
5500

Client: Agip KCO (Gama – Tekfen J.V.), Kazakhstan –http://www.agipkco.com

Kashagan Power Plant Project (KPP)

Project controls/planning activities of 2916 tones steel erection, 169.290 WDI piping fabrication and field erection, 990 ea. equipment erection& installation and painting and insulating works.

Final Project Value: US$ 362.250.000*

Planning Engineer, Tekfen Construction and Installation Co., Inc., AGIP KCO Gas Field Development Kashagan Main Works

START Date
END Date
Experience Hours (Planning & Scheduling)
4000
Experience Hours (Cost Management)
2000
Experience Hours (Forensic Analysis)
1500

Client: Agip KCO (Gama – Tekfen J.V.), Kazakhstan – http://www.agipkco.com

Kashagan Main Works Project, Trench-I& II (KMW, The world’s fifth largest oil field)