Quantity Survey

Project Planner, SITEI Srl, Madinaty City Project

START Date
END Date
Experience Hours (Planning & Scheduling)
1500
Experience Hours (Cost Management)
1000
Experience Hours (Forensic Analysis)
500

Development of the project baseline schedules, progress reports, an interim statement of payment, cost control, cash flow, document control, quantity survey, contract management, claims

Project Control Manager | Superintendent, TOA Corporation, Breakwater & Cargo Pier

START Date
Experience Hours (Planning & Scheduling)
500
Experience Hours (Cost Management)
500

Preparation of Design, Construction, and Technical Submittals.

Preparation, Monitoring, and updating Project Schedule.

Preparation of Quality Control and Safety Manual & Procedure.

Preparation of Implementing Rules & Regulation.

Preparation of Monitoring of Project Quantity Survey.

Preparation of Progress Billig & Collection.

Planning Engineer, Punj Lloyd Limited, Expansion & Revamping of KNPC Ahmadi Depot

START Date
Experience Hours (Planning & Scheduling)
1000
Experience Hours (Cost Management)
450
Experience Hours (Forensic Analysis)
0

Planning & Controlling Civil & Structural works for Project.

Quantity surveying.

Preparing monthly plans.

Preaparing Daily & Weekly reports.

Planning Engineer, Tekfen Construction and Installation Co., AGIP KCO Gas Field Development Kashagan Power Plant Project

START Date
END Date
Experience Hours (Planning & Scheduling)
5500
Experience Hours (Cost Management)
5500
Experience Hours (Forensic Analysis)
5500

Client: Agip KCO (Gama – Tekfen J.V.), Kazakhstan –http://www.agipkco.com

Kashagan Power Plant Project (KPP)

Project controls/planning activities of 2916 tones steel erection, 169.290 WDI piping fabrication and field erection, 990 ea. equipment erection& installation and painting and insulating works.

Final Project Value: US$ 362.250.000*

Planning Engineer, Tekfen Construction and Installation Co., Inc., AGIP KCO Gas Field Development Kashagan Main Works

START Date
END Date
Experience Hours (Planning & Scheduling)
4000
Experience Hours (Cost Management)
2000
Experience Hours (Forensic Analysis)
1500

Client: Agip KCO (Gama – Tekfen J.V.), Kazakhstan – http://www.agipkco.com

Kashagan Main Works Project, Trench-I& II (KMW, The world’s fifth largest oil field)

Quantity Surveyor & Planning Manager, IL&FS Engineering and Construction Company Limited, BOT infrastructure Project

START Date

Over Nine years of experience in the construction field. I am capable of working on a wide range of projects, particularly in the section of Quantity Survey, Planning & Project management in mainly National Highways and State Highways.

Project Engineer / Civil Engineer, Reinforced Earth India Pvt Ltd, PRECAST ARCH BRIDGE, REINFORCED EARTH WALL

J
Joe PS 👤 Member for 13 years 10 months
START Date

 

·         Establishment & Carrying out Site Operations

·         Construction Scheduling, Cost planning & controlling.

·         Monitoring the project progress & Ensuring the progress as per Schedule

·         Preparation of Progress reports on daily and monthly basis

Plannning Engineer, Saudi Oger, Al-Samriyah Farm, Development of King Abdullah Road

START Date
END Date

PRESENT JOB (country- Saudi Arabia) :

 

  • Working as a Planning Engineer  for Saudi Oger Ltd.  for the construction of “Al-Samriyah Farm” at Aamriyah, Riyadh from Oct.2010 till date.

 

  •  Worked with Planning Team in Head Office Riyadh for various projects “Bidding Proposal” from Jan 2010 to Sep. 2010.