develop and integrate individual schedules for Heavy Civil, Pipeline, Industrial and Piling divisions; quantity take-off, performance measurement, change management and cost processing ;

look ahead schedule, estimate / incorporate changes in scope of work during the course of project; analysed critical path and prepared mitigation plans for delayed works of quantified the delays;

reported earned value, SPI, CPI, labour, equipment and KPI progress curves and forecast / projections; performed forensic schedule analysis, quantified delays, estimated the change impact on the schedule / cost and perform delay / time impact analysis;

Cost Processing, Setup budgets, reported cost and revenue, integradted scheudle and cost;