Developed detailed and comprehensive baseline resource-loaded CPM schedules for several work packages.
-
Monitored actual site progress against the baseline schedule. Identified and reported variances, areas of concern and proposed measures for mitigation of delays.
-
Created recovery/acceleration plans and estimated necessary resource requirements.
-
Prepared look-ahead schedules, weekly & monthly schedule update and progress reports, including Cumulative Curves, resource histograms, manpower reports, percent complete and Earned Value reports.
-
Developed performance indicators and S-curves for various work packages.
-
Reviewed Subcontractor schedules and followed up on their progress to ensure conformance to the master schedule.
-
Monitored and reported on issues that could give rise to additional costs or delays.
-
Liaised with the Contract Administrator in preparation of claims and provided necessary supporting schedule information.
-
Drafted correspondence to the Owner’s Representative (Bechtel) and major Subcontractors
-
Ensured proper documentation and proof of potential claims. Tracked, and maintained a log for all delay/disruption events.
-
Performed scope verification / scope control: studied incoming “Issued for Construction” drawings and compared them to Bid Documents to identify variations or additional work.
-
Administered and prepared accounts for all Change Orders and cost reimbursable items.
-
Prepared a comprehensive assessment for the impact of material price escalation
-
Administered issuance of, and collected all necessary documentation for, all Project Retention Recovery Invoices.
-
Priced, negotiated & finalized Contract Variations with the Owner (West Delta Electricity Production Company) & Construction Manager (Bechtel).
Project Engineer, planner, CCC (Consolidated Contractors Company), Nubaria Power Station
START Date
END Date
Experience Hours (Planning & Scheduling)
1500
Experience Hours (Cost Management)
2000
Experience Hours (Forensic Analysis)
2500