A Statistical Approach to Estimating
Forum TopicHere we look at the principles and approaches to aid the project manager’s attempt to accurately estimate the duration and/or cost of a project http://ow.ly/SW2hK
Here we look at the principles and approaches to aid the project manager’s attempt to accurately estimate the duration and/or cost of a project http://ow.ly/SW2hK
I am trying to get a formula that acts as a "early warning" spot light in the number field against the finish variance e.g. if my base line finish is 40 days. What I want help with is the IF formulaif the finish is 40 days away or greater then the sy...
Hi Everyone,I would like to learn about LD. In one of the contract we have it is written as,Liquidity Damage will start after 15th Sep if the project is not complete . " The production would be only started upon completion of the project" which gives...
Here's a guide on how to base activity progress using a Unit Measurement In Primavera P6 http://ow.ly/T1qn9
Most people when faced with a painful decision such as having a leg amputated seek a valid second opinion! Sitting for the PMP exam is no different – regardless of whose course you have completed testing your knowledge against a different set of rep...
Dear All,Due to a variation order, the approved baseline programme has been revised with the incorporation of the variation item and few changes in the logic as mitigation.In the last updated programme (without variation), out of 11,000 activities ne...
Hello Everyone,I have been on the EPC projects from Contractors side till now for O & G company. I would like to learn when a engineering company is awarded FEED Study (Basis of Design & Statement of requirement is given by the Client) who from the e...
Dear All,Kindly share your input/thoughts for the following situation.After the baseline programme is approved.At the middle of the project a variation was issued by the Client and the Contractor issued an EOT notification for the delay in permit for...
Hello to everyone, i'm running a dissertation about project management and i would like to ask about those two methos.I want to know if we run the same project with CPM and then with MPM do i expect always the same resuls? Are there any articles abou...
As the subject indicates, I have encountered an issue whereby Pertmaster "runs out of memory" and will crash. There is no loss of data, but after several attempts to continue is has slowed to a crawl. Does anyone, or has anyone encountered this issu...
Hi All,1. In a sewergae line laying project, in a particular path there was enough float, say 60 days in the baseline programme.2. The Contractor started the works 30 days later than the plan date. At the time of investigation he found an underground...
Hi Guys,I prepare a recovery plan from last updated program, i was monitoring the progress based on total Budgeted Cost and all activities were Phisical % type. My project was in delay due to our mistake so i adjust the remaining duration by increasi...
Hi All,I am currently working on a schedule that requires us to do a monthly future bucket planning. We are looking at about 50 distinct resources and would like to find out what is the best way to do the loading, apart from manually keying the hours...
There has been a lot of talk recently about the decision by DCMA to raise the threshold for contracts requiring compliance reviews from $50 Million to $100 Million. On face value this might seem like the government is taking its foot off of the EVM p...
I am trying to create a test schedule in MS Project 2010. The problem is that with every new task that I create, there is no float associated with the tasks being entered. I have tried the following:1. Moved the Project Start date out six months or...
Hi, I would like to display a column that shows which predecessor activity is the main driver. Have tried a few things but no luck. Is there a way to do this? Thanks very much Dave
Hi All Pinoy PlannersI have a contact who is seaking two Spanish speaking planners for a long term contract in the Carribean.Permantent or contract.Send me a private message with your email and I will put you in touch.Best regardsMike Testro
Hi all,Please I am invited for an interview as a reporting engineer in BOQ department, can someone tell me expected interview questionsThanks
Here's a great explanation which helps understand Primavera P6 EPPM scheduling privileges with limited project data privileges http://ow.ly/TnYO5
Hi Guys,I have created a formula column called ductwork, which simply outputs a 1 if the task name contains the word ductwork and 0 if not. My formula works great, however I would now like to create a filter to hide all 0's in a column, I have tried ...