New Tasks With '0' Float Throughout the Schedule

I am trying to create a test schedule in MS Project 2010.  The problem is that with every new task that I create, there is no float associated with the tasks being entered.  I have tried the following:

1. Moved the Project Start date out six months or more

2. Ensured all of the tasks were linked

3. Added a Deadline Date for the last tasks in the Network

4. Changed all Constraint Types to ASAP

No matter what I have done, there has been minimum to no float in this test schedule.  Can someone tell me what I"m missing on this?

M
Mike Testro 👤 Member for 20 years 5 months

Hi Reggie

If you have a continuous cascade of FS links then tasks will alaways be critical.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts