I am trying to create a test schedule in MS Project 2010. The problem is that with every new task that I create, there is no float associated with the tasks being entered. I have tried the following:
1. Moved the Project Start date out six months or more
2. Ensured all of the tasks were linked
3. Added a Deadline Date for the last tasks in the Network
4. Changed all Constraint Types to ASAP
No matter what I have done, there has been minimum to no float in this test schedule. Can someone tell me what I"m missing on this?
Hi Reggie
If you have a continuous cascade of FS links then tasks will alaways be critical.
Best regards
Mike Testro