Earliest Finish Date
Wiki PageLatest Finish Date
Wiki PageOFC Laying
Wiki PageOFC LayingBy Using Concrete/Road Cutter EquipmentResourcesSurvey Team of 4 (1 Suveyor , 3 Assistants)Equipment with Operator and HelperCutting Line Marking team ( 2-3 Persons)OFC cable laying team ( 4 Persons)Splicing team (2 technicians )Productiv...
Fibre Cables
Wiki PageThere are 4 phases to laying fibre cables - The laying of the duct, the pulling of the fibre cable, the splicing/terminating of the cable and the testing of the cable.The production rate for the laying of the duct will be as any similar small diamete...
Traditional mass fill foundations
Wiki PageIncludes excavation and concrete pour.Assumes 450mm wide, average of 1.5m deep, No earthwork support, reinforcement or claymaster.35 linear metres per day per gang.
creating a program
Forum TopicI asked my immediate superior why our project baseline and tender projects : 1) activity duration are almost the same in every WBS, 2.) why the relationships are SS & FF and the lag are almost the same and 3) why the activity bars are almost ove...
Only allowing a certain user to view part of the overall Programme in Primavera Project Management
Forum TopicDoes anybody know if it is possible to only allow a certain user on project management to view a part of a programme rather than all the activites? I either need to only allow access to certain activites or only allow access to a certain part of the ...
Planned Values changing when saving the plan as itself and applying it as a baseline
Forum TopicI have re-baselined an existing programme and reprofiled the spend but kept the old Planned Values. I have gone and copied the programme to use as a progress and applied the re-baselined programme as a new baseline, this has caused my Planned Values ...
Barrel Vaulted Timber Diagrid Roof Construction
Forum TopicI am currently undertaking a project that incorportaes a Glulam Timber Diagrid Barrel Vaulted Roof. Has anyone here had any experience of such a form of construction that they would be willing to pass on. The arch spans approx 38M and maed up of 4m g...
Grouping band
Forum Topicif the activities used more than calendar how p6 calculate the variance finish or start for grouping band
Help - Early start / Finish dates dont equal the Assign Baseline (Current project) ????
Forum TopicHas anyone ever come accross this problem yet??? My early start and finish dates dont match my Assign baseline ( current Project) dates ? they should match - and no I have not re-scheduled, and it is on a stand alone version so it is not someone that...
Road Basecourse
Wiki PageA good rule of thumb for the construction of road basecourseUrban environment:Spread & Compact Production = 30m3/hrTrimming Production = 250m2/hrRural environment:Spread & Compact Production = 50m3/hrTrimming Production = 350m2/hr
Working Platforms
Wiki PageWorking PlatformsTask / DescriptionSlow Ave Fast Units Metal KwikStage, 5 Boards with 2m lifts11.1 11.9 12.5 m run/hr Metal KwikStage, 5 Boards with 3m lifts9.1 10.0 10.5 m run/hr Metal KwikStage, House Scaffold with 3 lifts2.8 3.2 3.8 m run/h...
Waterproofing
Wiki PageTask / DescriptionSlow Ave Fast Units Asphalt coatings, horizontal surfaces3.5 4.2 5.8 m2/hr Asphalt coatings, vertical surfaces1.2 1.7 2.2 m2/hr Bituminous Brushed application, 2 coats4.8 5.0 6.3 m2/hr Bituminous Brushed application, 3 coats3...
Trackwork
Wiki PageTrackwork...Task / DescriptionSlow Ave Fast Units FST Floating Track Slab, side restraints9.6 - - m/day FST Floating Track Slab, resin pads10.2 - - m/day FST Floating Track Slab, slab units10.6 - - m/day PCBT - Pre-cast Concrete Block Tr...
Tower Cranes
Wiki PageTower Cranes...Task / DescriptionSlow Ave Fast Units Erect and Setup 50m gib- 11.0 7.5 days Dismantle 50m gib- 10.0 - days Lifting, Reinforcement Bins and Cages, 1st 15m lift- 3.2 - mins/lift Lifting, Reinforcement Bins and Cages, above 1...
Resource and Cost Planning Steps
Forum TopicTo All:hello people. i am just registered to this awesome site. maybe it's been discussed here many times but pardon me i'm just new to this site.will somebody guide me how to have steps on resource and cost allocation? or where i will go from here?t...
Steel Strutting
Wiki PageSteel Strutting...Task / DescriptionSlow Ave Fast Units Horizontal heavy duty strutting- 2.0 - days/no Diagonal heavy duty strutting- 6.0 - days/no
Soil Mix Walls
Wiki PageSoil Mix Walls...Task / DescriptionSlow Ave Fast Units Three Auger Drill, cement and cure3.8 4.5 6.4 m/day