Biggest challenges bridging the gap between IT department?

Forum Topic

 I'm a QA engineer and often find myself stuck between technology and business people who speak 2 speak totally different languages. I'd like to improve communication between groups, what are some of the biggest challenges you face as project manager...

Aug 14, 2013

calculating multiple float paths

Forum Topic

I am having a problem with my schedule in calculating multiple float pathsThe contractors schedule submitted to me has over 6000 activities this is my first month on this project and I am not very familiar with this schedule. For some reason whenever...

Aug 14, 2013

Sr. Planners FPSO / Houston, Texas

Forum Topic

SBM Offshore is currently looking for Sr. Planners with FPSO experience.  Positions are direct hire and are in Houston, Texas, USA.  Please visit our website at www.sbmoffshore.com and select the "Working with us" tab.   Submit your CV for the Sr. Pl...

Aug 14, 2013

Importing/Exporting from/to CSV

Forum Topic

Hello Vladimir,I have created an Excell Macro that will generate an "oper" document and save it as a text tab delimited file, in order to import activities into Spider. I have set up the Macro to create for all activities all the "Standard" column va...

Aug 14, 2013

Schedule Referencing / Numbering

Forum Topic

I need to know where I can apply a schedule number and revision number to the schedule.I also need to know how this information can be generated in the border. I have tried this in the page set up but when I open up another project the information th...

Aug 15, 2013

About Consumable Resources / Materials and Spatial Resources

Forum Topic

The two most common categories of resources on CPM software are; renewable resources and consumable resources.Renewable resources are renewed as soon as a particular activity using the resource ends.   Only the total resource use at every time instan...

Aug 16, 2013

S-Curve on P6

Forum Topic

Hi There,Please advise if we can generate an S-curve on P6 without any resources and cost on the activities. I've been trying to do this but it seems that the software cannot do it.Any suggestions?Thanks.

Aug 20, 2013

S-Curve on P6

Forum Topic

Hi There,Please advise if we can generate an S-curve on P6 without any resources and cost on the activities. I've been trying to do this but it seems that the software cannot do it.Any suggestions?Thanks.

Aug 20, 2013

Predecessor Bar Color?

Forum Topic

Hi, I was learning how to use Primavera back in college around 2007 and had not use it since. I just started using it again for Scheduling in my new office. In the previous version that I used when I was in school, when you linked two activities, the...

Aug 21, 2013

Schedule task based on resource availability

Forum Topic

Hi, I want to schedule a task based on the resource availability. As per plan:Project Start date is 02.06.2013Piling Work Starts on 02.06.2013 by default, duration is 90 days, end date of piling is  say, 01.09.2013My resource , the piling rig will be...

Aug 21, 2013

Statutory undertaker

Forum Topic

Hi, The contractor was handed over the land to build the road for the govt. agency. Some utilities need to be shifted in which statutory undertakers (SU) were involved. As per the contract, the contractor needs to pursue the matter with the SU for ob...

Aug 21, 2013

Level of effort

Forum Topic

Hi All. Can anyone please help? I am trying to creat a level of effort activity and have linked it as a SS with its predecessor and FF with its successor both with zero lag. When I schedule, the level of effort activity only shows the start date as s...

Aug 22, 2013

Baseline is not correct

Forum Topic

I am new to P6 and I'm new to Planning Planet.So far I have;I am trying to compare 2 schedules; 'Pre-Impact' and 'Post-Impact'.  I have progressed the two schedules to different dates (including actual dates and any re-sequencing).Both of the above s...

Aug 23, 2013

Filter for completed critical activities

Forum Topic

I have a schedule that is progressed to a specific date.  I want to filter it to show the critical path activities INCLUDING the completed critical path activities.It seems that once a critical path activity is complete, P6 no longer recognizes it as...

Aug 23, 2013

Data date change, critical path changed?

Forum Topic

Hi,I have a fixed schedule from previous project and I want to use it on another project with exact same activities, relationship, and everything. But when I changed the data date, the critical path also changed. Does anyone know why is this happenin...

Aug 23, 2013

Importing of P3 file into Primavera P6

Forum Topic

I am able to import P3 files(activities around 3000++) into Primavera P6, however, i am not able to import a 17,000++ activities file into P6, i am getting the message of Unable to Open "FileName" in directory C:\P3WIN\PROJECTS. so could someone give...

Aug 23, 2013

Career towards Project Management

Forum Topic

hi to all dear expertsi need a piece of advice from u guys. I m doing job as planning engineer since 6 years in a construction oil & gas co. I have done PMP and now want to grow more in project management field. I m planning to do MS-PM. its a 2 year...

Aug 24, 2013