Hi all,
I am facing a problem.
I have created a programme and filtered some activities using Activity codes.
I want the resource usage profile for the filtered activities alone.
How can this be done?
-AJ
Hi all,
I am facing a problem.
I have created a programme and filtered some activities using Activity codes.
I want the resource usage profile for the filtered activities alone.
How can this be done?
-AJ
Hi Asish,
You can filter the group of activities using activity codes; however it is not possible to show or filter only the lists of the Resources assigned to those activities displayed while currently showing the “Resource Usage Profile” bottom layout.
I suggest you may use the functionality of “Tracking” which show only those resources assigned to each WBS level.
I hope the above assists you.
Cheers,
Arnold
I am using Primavera P6 R8.2.