Search

pre commissioning and commissioning

Forum Topic

Pleases, can any one tell us how to make pre commissioning progress or to give us examples of progress calculation in oil and gas projects?

May 15, 2018

Database Cleanup - SQLlite - R8.4

Forum Topic

After reaching the 4GB limit on the XE database for the 1000th time I decided to just switch over to SQLlite. I have no reached the point where even my SQLlite database is bloated with POBS and old codes. Can someone tell me how to cleanup my sqllite...

May 15, 2018

Performance % Complete Change After Assigning Baseline

Forum Topic

As per the above subject, there's a difference in Performance % complete before and after I add & assigne a baseline.that difference is not for all items, some items doesn't change.I need to understand what happened.

May 21, 2018

Is it possible to create new indicator icons

Forum Topic

Planners, Odd question but does anybody know if it is possible to create new indicator icons in P6 EPPM? My boss wants a P6 programme to Match and MSP programme that is using smiley faces.  We are running P6 EPPM 17.12.1 Kind regardsSebastian 

May 23, 2018

P6 Longest Path made up of 16 multiple float paths

Forum Topic

I have a preliminary schedule with no actuals from a contractor that I discovered has a critical or longest path made up of 16 multiple float paths base on free float. Most of the float paths are 1 or 2 activities. There are only 2 calendars used a 5...

May 23, 2018

P6 Reports - Data fields empty

Forum Topic

When I run some reports for time distributed units, the data fields are empty. However, if I step through the reports wizard and run the report from there the data appears. Currently using R15.2 but encountered the same problem in a previous version....

May 24, 2018

Assign other progam as a baseline -Synchro

Forum Topic

 Hi there,  have 2.sp files and both has been  exported form P6. one is baseline(No progress) and other is updated . how can I assign the baseline over the updated one ? Thank you

May 27, 2018

Error in P6 R8.2- Application Event

Forum Topic

Hello,Iam doing a Time impact analysis and in the Projects layout , i was copying and pasting the baseline to create more windows for analysis. After doing this and completing few windows, there was an error as shown below,"An application event has b...

May 28, 2018

Hours issue dragging 1 day activities over days

Forum Topic

Hi There, I am currently encountering this issue in prog. One day activities are dragged over two days. I checked the user preference, calendar, and admin preference all have same duration; my day has 8 hour duration and it starts from 8am but in som...

May 29, 2018

Importing XML to P6 error

Forum Topic

Morning all, I'm trying to import an XML/MPP file into P6 v8.2 and keep getting an error  SEVERE: Unable to invoke setHoursPerYear on business object Calendar. Value for field "HoursPerYear" in Calendar may not be set to greater than 8784. com.primav...

May 30, 2018

Monte Carlo Simulation

Forum Topic

Hello Our company would like to do a monte carlo/probability analysis on a financial model which has a number of variables which includes a number of funding/profit sources, borrowing sources, interest rates, years/duration's, etc. We are trying to d...

May 31, 2018

A survey on Impact of construction programme and cash flow tecniques

Forum Topic

Dear Participant,I invite you to participate in a research study entitled-IMPACT OF CONSTRUCTION PROGRAMME & CASH FLOW ON CONTRACTOR’S PROFITABILITY I am currently enrolled in the MBA (Construction and Real Estate) at the University College of Estate...

May 31, 2018

P6 database configuration

Forum Topic

If I have not been told which database congfiguration to to use can I use any of the 3 offered when I log in for the first time or does it actually matter which one I use.The three options are Oracle, MS SQL Server or Primavera compression server

May 31, 2018

Hide Activities in P6

Forum Topic

Hello, I have been trying to hide activities in my P6 Schedule. I tried using filter, but it changes the duration of the project.I wish to hide activities, that retains my Project Schedule. Best Regards,Nisha Joseph

Jun 1, 2018

Sample of xer file

Forum Topic

Dear All, who can share cost loaded schedule in xer ? P6 thanks in advance Regards,Elnur

Jun 4, 2018

DACE labor productivity norms

Forum Topic

Hi everybody,I am leading the planning office of my company mainly involved as EPC contractor in industrial plants and infrastructures.After many years, I have the opportunity to purchase a database of labor productivity norms. I am trying to find a ...

Jun 4, 2018

Activities in which WBS Level in any view

Forum Topic

All, Is there a way of showing the WBS level in any view? Even a formulae in global change to show the WBS level that the activity is in would help. Thanks Pranab

Jun 4, 2018