Hi everyone,
When I update my baseline in Primavera P6, an error occurs as follow "An application events has been intercepted. Please note the reference code for reference. Event code F429B079". So, I can not use update BL function in P6 anymore.
Could you help/instruct me how to solve this problem.
Thanks so much,
Viet Tran,
glad I could help
Dear Zoltan Palffy,
Thanks for your consulting. It's now running ok after I re-installed the correct Java version integrated P6.
Thanks and regards,
Viet Tran,
you have the incorrect java version
to resolve this issue, please follow these instructions: