Assign other progam as a baseline -Synchro
Hi there,
have 2.sp files and both has been exported form P6. one is baseline(No progress) and other is updated .
how can I assign the baseline over the updated one ?
Thank you
Top Posters
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts
Dear colleague:
proceed as MR. PT Thomas described.
Just take care that each activity in one file match with the right activity in the other file, through the Act ID.
This is the only way for P6 to joint the current activity with its baseline.
Regards