Search

Exporting Budgeted Units Not Match

Forum Topic

Hi ,I have  an existing & repaired schedule with budgeted units(Labor & Non Labor). When i exported the report in time interval, only shown was the labor Units.hope somebody can help me.Thank You!

May 30, 2013

Ground Rules for Gadgets in Meetings?

Forum Topic

With so many choices of technology that we take to meetings, some of which is essential for the meeting, how do you control gadget use beyond silencing your phones? What ground rules do you have for gadget use in meetings? http://ow.ly/lxEfz

May 30, 2013

User import permissions

Forum Topic

I am trying to allow a user within Primavera to be able to import schedules.  I have his global permissions set to allow "import project managment xer, mpp, mpx and p3" and I have his project permissions set to be able to "create project within EPS"....

May 31, 2013

Having an issue altering the finish date for an activity

Forum Topic

I have an activity in which I know the exact date it will finish, however I am having trouble adjusting the finish date in my schedule.All predecessing activities have been completed, so it's not being pushed back because of that.Additionally, I have...

Jun 1, 2013

Primavera Risk Analysis - Guide Book

Forum Topic

Afternoon all,   I have recently been on a PRA course and was given a short manual from the training provider. Does anybody know of any published books that can help with using PRA? Regards Chris

Jun 3, 2013

Original Duration

Forum Topic

Hi!I have a programme that is going to last longer than originally planned, but it confuses me that when I updated it, the summary value of Original Duration column appeared to be the same as summary value of At Completion Duration column. OD of sing...

Jun 3, 2013

Actual Labour Units

Forum Topic

Hi, The actual units of few activities found changing to(equal to  the duration %) for the activity’s percentage complete type was Physical percentage complete.   Problem was fixed by removing the option recalculate actual units and costs when durati...

Jun 4, 2013

Identifying Cost and Schedule Risk Drivers with Acumen Risk

Forum Topic

The Risk Drivers report from Acumen Risk provides a unique insight into true cost and schedule risk drivers in an easy to understand tornado chart.  Using a metric called Schedule Contribution Factor, Acumen Risk reports activities or risk events wit...

Jun 4, 2013

P6 Calender Settings

Forum Topic

I face a problem as follows: I am demonstrating the problem through a sample network of 2 activities linked finish to start and both of original duration of 6d The Project and Activity Calender is following a 6 days Work Week, 8 hours Work per day 08...

Jun 5, 2013

Internet Explorer v 10

Forum Topic

Hi AllI was not able to enter any comment in PP or Linked In following an update from Windows.I now use Google Chrome and the problem is solved.Best regardsMike Testro

Jun 5, 2013

"time distributed data"section in the "user preferences" dialog box

Forum Topic

hiin the "time distributed data" section in the user preferences dialog box what is the difference between "remaining early dates" and "forcast dates" and how are they entered or calculated in the software? also what does the 2 options in the "displa...

Jun 5, 2013

Recalculate assignment costs after scheduling

Forum Topic

hithese is an option in the "schedule options" dialog box in primavera p6 that i can't figure out what does it do it is named"recalculate assignment costs after scheduling" i have heared it is used for resources with different price/units but i can't...

Jun 5, 2013

Links Between Projects

Forum Topic

Hello,My programme has some activities that are linked to activities in the Client's programme (local copy on my dbase). i.e. Completion of certain activities in my Client's programme defines an 'access' milestone in my programme.What does P6 do with...

Jun 6, 2013

Links Between Projects

Forum Topic

Hello,My programme has some activities that are linked to activities in the Client's programme (local copy on my dbase). i.e. Completion of certain activities in my Client's programme defines an 'access' milestone in my programme.What does P6 do with...

Jun 6, 2013

Filtering out the spotlighted activities

Forum Topic

Hi there, Can anyone tell me how when using the spotlight to highlight a period of time I can show on the task list only those highlighted and nothing else? I've tried a filter but can't seem to find anything that will select a range of dates rather ...

Jun 6, 2013

Filtering out the spotlighted activities

Forum Topic

Hi there, Can anyone tell me how when using the spotlight to highlight a period of time I can show on the task list only those highlighted and nothing else? I've tried a filter but can't seem to find anything that will select a range of dates rather ...

Jun 6, 2013