Original Duration

Hi!

I have a programme that is going to last longer than originally planned, but it confuses me that when I updated it, the summary value of Original Duration column appeared to be the same as summary value of At Completion Duration column. OD of single activities is fine, but summary value is different to before programme was updated. Do you know if it is something with in settings?

Thanks,