Contract versus programme
Forum TopicHi planners, I am not sure about something contractually. Lets say Week 1 - Task A- excavation delayed by information required from architect. 3 weeks EOT granted. Week 2 – Task B – Construct new foundation, ahead 1 week due to faster excavation com...