Showing Early and Late Cost curves in P6

I have a baseline cost loaded schedule that I want to see cost curve based upon the early and late dates. The profile can generate early, but not late. Is there a way to do this? Also is there a way to show in tabular form the cost by early and late dates?

K
Khaja Sharief 👤 Member for 17 years 8 months

Select activity usage/resource usage profile. Now right click on the graph and select activity usage profile options/ resource usage profile options.  Under bars/curves area, select the remaining early or remaining late. You can play around this, you can veiw this in terms of units as well as costs. 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts