Logic link question

Hi all,

I wonder if someone could help me.

I have several activities that start at the same time and one that starts later

A 2-12-11

B 2-12-11

C 2-12-11

D 10-12-11

I want them all to link to activity E so that E starts on the 2-12-11 however when I use a SS link it ignores the early date and starts on the 10-12-11 instead.  Is there a way of linking all the activities together and get E to start 2-12-11?

thanks in advance,

 

Thom

R
Rafael Davila 👤 Member for 22 years 3 months

If what you want is to setup e (task no 9) to start after any of a/b/c/d starts and they are independent to each other this is difficult to model by most CPM software as the majority does not allow you to create driving links to/from summary bars.

For MSP this is a walk on a beautiful spring morning along Memorial Drive on Charles River.

Photobucket

Sorry I could not make a correction to task 9 name, I deleted the file, I know with regard to summary bar MSP is more powerful than most other. Maybe LOE activities in P6 can handle this.

I am trying to model this with cumbersome conditional switches on Spider Project my software of choice got it for 2 activities with the use of formulas and a script but for 3 activities it is becoming very complicated. I have modeled this with cumbersome procedure using resource leveling and resource consumption and creation available in Spider. This allows for even more complicated scenarios at the cost of even more complicated setup.

I always dreamed of more intelligent links to a group of activities where ease of setup and transparency is key.

Best regards,

Rafael

M
Mike Testro 👤 Member for 20 years 5 months

Hi Thomas

Set up a milestone as your start date and link that FS to all your other activities.

Never Ever use FF SS links.

Best regards

Mike Testro

S
Sandy Matheson 👤 Member for 21 years 8 months

You need to think clearly through your logic here.  By putting SS between A, B, C & D and your activity E they you are saying activity E cannot start until each of these activities has started.  The software calculation is correctly showing activity E start as 10-12-11.  If you say activity E can/should start on 2-12-11 then there is not a SS relationship betweend D and E.  This is fairly basic understaning of CPM logic.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts