Search

Histogram To Count Tasks

Forum Topic

Hi All, I'm trying to create a histogram that counts the number of Tasks at the instant in time that have a been alllocated with a cost centre value, rather unsuccessfully at the moment. Does anyone know how? Thanks, Chris.

Aug 6, 2012

production rate

Forum Topic

Hi friends,Anybody pls reply what is the production rate for sructural steel work(light, heavy and medium).your help in this regard is highly appreciated.Regards,Sunil.

Aug 7, 2012

Generating an Early, Late, & Planned Curve in P6

Forum Topic

In P3, users could produce an Early, Late, & Planned Curve.  P6 doesn't do this.  I am able to produce an Early & Late Resource curve by copy/pasting the data from the resource assignments view into an excel spreadsheet, but I cannot produce a planne...

Aug 7, 2012

Manually changing remaing durations

Forum Topic

Question: What is causing us to have to input six or seven times a remaining duration. Example: we want to show RD as 5 days, however, when we input, in comes up as 3.66. Then we put 5 days again and we get 3.97. This goes on until we finally get MP ...

Aug 8, 2012

Link between RD & P%C

Forum Topic

Question: Which task duration type is the best to use Fixed Duration, Fixed Work, or Fixed Units when unlinking remaining duration and physical percent complete?

Aug 8, 2012

Microsoft Project 2013 and Primavera P6

Forum Topic

Hi Guys, New test results - Check out using the new Microsoft Project 2013 XML format in conjunction with Primavera P6 R8.2 http://ow.ly/cOOOe Emily

Aug 8, 2012

Primavera P6 and Microsoft Project 2013

Forum Topic

Hi Guys, New test results - Check out using the new Microsoft Project 2013 XML format in conjunction with Primavera P6 R8.2 http://ow.ly/cOOOe Emily

Aug 8, 2012

Above ground pipeline activities

Forum Topic

Dear All,I was assigned with a 50km long above ground pipeline installation project in saudi arabia. I had worked before in underground pipeline installation project. Although i know the basic wbs structure of above ground pipeline installation i don...

Aug 8, 2012

Resource Distribution

Forum Topic

Hi Guys,I want to distribute particular resource throughout the duration of the Activity "A", but when I assigned the resource and generate the report it has been assigned whole resource to the start day of the activity only.But I created new project...

Aug 9, 2012

Planned completion date and completion date

Forum Topic

Morning, Pretty new to the concepts of planned completion date/completion date and terminal float, so pls bear with me. Should planned completion date and completion date be the same on an initial programme submitted for acceptance? Thanks.    

Aug 9, 2012

Demonstrate Disruption

Forum Topic

Hi There, Does anyone have handy examples of methods to demonstrate Disruption. Such as the Measured Mile. Kind Regards Stephen

Aug 9, 2012

3D Work Breakdown Structure

Forum Topic

 Short video presention about 3D WBS : http://www.youtube.com/watch?v=aj2W-wJc5GA&feature=plcpMore details, my blog about 3D WBS: http://3d-wbs.blogspot.fr/

Aug 9, 2012

change asta calendar

Forum Topic

Hi there,Could anyone please explain the method to changing the calendar on asta so that selected days become 24hours and not only 8hours?Thank youVas

Aug 9, 2012

Base Line

Forum Topic

hi anybody can answerI updated my progress in P6 and i want this updated shedule as a new baseline. How can i change it in primavera P6? 

Aug 10, 2012

Linking Progress

Forum Topic

First post to the forum so please bear with me.   I am trying to link % complete on two or three seperate tasks but not having a lot of success. I want to be able to enter the % complete on one bar but at the same time it enters the same the summary ...

Aug 10, 2012

Tracking Gantt Chart in P6

Forum Topic

I would like to know if it is possible to create a “Tracking Gantt chart” in P6 just like that in MS Project.  If anyone has an idea, I will appreciate it if that person sends me clear instruction or point me to a manual or tutorial.

Aug 10, 2012

Default Units / Time

Forum Topic

Is there a way to change Default Units/Time and Max Units/Time from percentages to integers?  I am pretty sure I was able to this in the past, but do not seem to be able to do it now.  Using P6 8.2.  Thanks.Note: Currently 100% = 1 man day of 10 hour...

Aug 10, 2012