Question: What is causing us to have to input six or seven times a remaining duration. Example: we want to show RD as 5 days, however, when we input, in comes up as 3.66. Then we put 5 days again and we get 3.97. This goes on until we finally get MP to show 5. Can anyone help us resolve this?
Manually changing remaing durations
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
try to check your default hours per day in Project Options. Your default setting should match with your project calendar.