Question: Which task duration type is the best to use Fixed Duration, Fixed Work, or Fixed Units when unlinking remaining duration and physical percent complete?
Link between RD & P%C
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
James,
Physical Percent Complete cannot be linked to Actual / Remaining Duration
Only % Complete and Work % Complete can be unlinked from Actual Duration, they are linked by default
Task Duration type is being used by MSP to compute the task duration / resource assignment units / resource assignment work when you change a value in the assignment; it is not used when you update the project either manually or automatically