Question: Which task duration type is the best to use Fixed Duration, Fixed Work, or Fixed Units when unlinking remaining duration and physical percent complete?

A
Alexandre Faulx-Briole 👤 Member for 23 years 6 months

James,

Physical Percent Complete cannot be linked to Actual / Remaining Duration

Only % Complete and Work % Complete can be unlinked from Actual Duration, they are linked by default

Task Duration type is being used by MSP to compute the task duration / resource assignment units / resource assignment work when you change a value in the assignment; it is not used when you update the project either manually or automatically

Alexandre