Question: How can we stop MP from automatically giving an activity a constraint after updating baseline?
MP automatically putting Constraints on activties
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
James,
when you update the project with the option "Reschedule uncompleted work after the status date" (freely translated from French), MS Project assigns a Start No Earlier Than constraint to the unstarted activities, and a Resume Date to the activities which had started before the update and are suspended
there is no way to refuse the constraint, or the activity will be scheduled back in the past
Alexandre