MP automatically putting Constraints on activties

Question: How can we stop MP from automatically giving an activity a constraint after updating baseline?

A
Alexandre Faulx-Briole 👤 Member for 23 years 6 months

James,

when you update the project with the option "Reschedule uncompleted work after the status date" (freely translated from French), MS Project assigns a Start No Earlier Than constraint to the unstarted activities, and a Resume Date to the activities which had started before the update and are suspended

there is no way to refuse the constraint, or the activity will be scheduled back in the past

Alexandre