Reply of Client for my EOT Claim

Forum Topic

 Hi Experts; Our project was extended to 31st July but due to lack of funds from the client it has been delayed again.I submitted the schedule to the client woth a new Expected finish date.In reply to my EOT,I received the Following reply from the cl...

Jul 29, 2012

Event code CVRJC-2214-A"???

Forum Topic

 Hi to all,When I imported P6.0 Xer file this message appeared. "An application event has been intercepted. Please note the event code for reference.Event code   CVRJC-2214-A"How to fix this problem???

Jul 29, 2012

Print Primavera P6 calendars

Forum Topic

 Hi everyone, Is there any way to print calendars in Primavera P6? What I would like to achieve is to be able to print a page that contains P6 monthly calendars from the project start date to the project end date. I have not found any option to do th...

Jul 30, 2012

Maintaining Activity Code

Forum Topic

Hi Everyone, i have a query about maintaining activity codes in P6. As we receive new files every month, how can we check whether proper code values are assigned to the respective activities or not?

Jul 30, 2012

Level Of Effort progress updated

Forum Topic

Hi All, Just wonder how normally you update your level of effort schedule activities (when you are running live schedule)? Do you change it to task dependent by the time the baseline been finalized?

Jul 31, 2012

Working hours

Forum Topic

Hi to all I am a junior planning working in oil and gas and doing scheduling.My question is that my company works 10 hours a day and i developed a calender of my company setup up the timing from 6 am- 4:30 pm but when i assing resources and insert wo...

Jul 31, 2012

Update Progress Tool in P6

Forum Topic

Hi planners. I have a question about "Update Progress" tool in P6. I have a project on time but out of budget, so I want to update it using "Update Progress" only dates, not actual amount of resources because of resources must be update manually. How...

Aug 1, 2012

Resource Loading of Ongoing Schedule

Forum Topic

Hello guys, I would like to seek advices from you guys whom I know are more adept on this Project Planning Field. My problem is We are using a schedule with no resource/man hour loading. And now the client wants me to resource load the schedule, is t...

Aug 1, 2012

Earned Labor Units

Forum Topic

Hi Everyone, Can anybody advise on how to disconnect the duration from the labor units. This is possible in P3 (in options) , how ever in P6 once you change the remaining duration the earned labor units automatically changed. I dont need to change th...

Aug 1, 2012

Importing Financial Period Actual Units into P6 using a Spraedsheet

Forum Topic

I want to use Excel to import Actual Units into P6 for Financial Periods. I have set up Financial periods & a test project. I export data to an Excel Spreadsheet (the Resources Tab), which gives me a template. If there are actual hours in P6, then th...

Aug 2, 2012

Modify critical path

Forum Topic

Hi allThere is a very big project with its starting date and finishing date. However, I do not want the critical path to go till the end. Along the project there is a milestone which I want to be the end of the critical path. What happens after that ...

Aug 2, 2012

Opening XER file from P6.r8 in P6.r7

Forum Topic

Hi Everyone,We are in transition period moving from P6r.7 to P6r.8.2 and we still have some project and 7 while we started some project in 8.I am facing a problem in one my peoject where there is part of the project has been build in r.8 and I need t...

Aug 2, 2012

EARLY START AND LATE START S-CURVE

Forum Topic

Hi,Appreciate if somebody could show me how to fill up the early start and late start date columns as data cannot be entered and on ly show display dates that are similar to START and FINISH dates. I need these info to construct my early start and la...

Aug 5, 2012

EARLY START AND LATE START S-CURVE

Forum Topic

Hi,Appreciate if somebody could show me how to fill up the early start and late start date columns as data cannot be entered and on ly show display dates that are similar to START and FINISH dates. I need these info to construct my early start and la...

Aug 5, 2012

Closeout Programme

Forum Topic

What is a closeout programme,  Is there any difference between main baseline and closeout programme Thanks

Aug 6, 2012

SDEF File to XER File ( vice versa )

Forum Topic

 Hi, Does somebody knows how to generate SDEF File and to convert to P6 XER File or vice versa. In addition, what is the advantage of using SDEF File since this is my first time I heard this SDEF File.  Any help is very much appreciated.

Aug 6, 2012

P6 Integration API for running data exchange

Forum Topic

I want to show  my schedule from Primavera as Time-Distance-Diagram in TILOS. To get the data-exchange running it seems that you need to install P6 Integration API first?

Aug 6, 2012