I want to use Excel to import Actual Units into P6 for Financial Periods.
I have set up Financial periods & a test project. I export data to an Excel Spreadsheet (the Resources Tab), which gives me a template. If there are actual hours in P6, then this comes across into P6.
However, if I update the actual hours in the spreadsheet & then import back into P6, the hours I changed/added do not come across.
Has anyone tried this & have a solution?