Update Progress Tool in P6

Hi planners.

I have a question about "Update Progress" tool in P6. I have a project on time but out of budget, so I want to update it using "Update Progress" only dates, not actual amount of resources because of resources must be update manually. However, "Update Progress" updates both at the same time, dates and actual resources amount

Is it possible to use this tool in order to update only date but not actual resources amount?.

Thanks a lot for your comments.

 

Alfredo

M
Mohd Nizam 👤 Member for 21 years 2 months

Auto compute actual are meant for Earned Value cost based on the actual progress. it does not compute an actual cost. for this, you have to key in manually and then only you will be able to identified which activities is over budget.

S
SM PUM 👤 Member for 14 years 7 months

make sure that "Auto compute actuals" option for each resource is checked off.

 

Regards

SM

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts