FIlter Problem
Forum TopicHi-experts I am using a UD filter 10 months lookahed filter , while applying this filter the WBS level 1 summary bar and duration not reducing. while using P6 inbuilt filter it is working fine, Please advise , Best Regards
Hi-experts I am using a UD filter 10 months lookahed filter , while applying this filter the WBS level 1 summary bar and duration not reducing. while using P6 inbuilt filter it is working fine, Please advise , Best Regards
Hello Fellow Planners, Trying to change the thickness of critical links so they are more visible - only seem to be able to change color. Anyone know how to change thickness? Thank you in anticipation, Craig Adams
Hello Planners, Am having difficulty in schedule I've created where I've assigned particular resources that use a 5 day calendar instead of the 6 day applied to the rest of the project. All good as I know no concrete pours will occour on a Saturday h...
Hi, Since I only have experience of Primavera version 6, can someone please confirm the difference between version 3 and version 6? Many thanks Danielle
Hi, Since I only have experience of Primavera version 6, can someone please confirm the difference between version 3 and version 6? Many thanks Danielle
Hi all, I have problem with my P6. I'm using P6.7. I cant excess primavera n need to configure the database connection. I tried all the username and password as suggested by members in the forum but none of them works. Can anyone help me regarding th...
hi to all, Is there anyone who had a Project planning and control (using P6) manual by paul harris. kindly inform me where i can get it for free. thank you
dear all,hoa to change the cut off date in P6? in the schedule the cut off date falls every sunday, but i want it to be change every friday. thanks
Hi, How can be the activities without acitivity codes assigned be filtered. As there are many different depts and difft activity codes. Thanks in Advance.
Using P 6.2.1, I want to import into the WBS table via excel (to save typing). Anyone know how to do this? Thanks, Mark
Help. I want to to take 3 separate projects and combine into one. Each one will be used for either Primary, Secondary or Tertiary. How can you do this combine in P6? Thanks, James B.
If I run a report to view all my project resource budgeted hours everything shows up. In another report I created to show budgeted hours, earned hours, at completion, and scheduled % complete and then set my filter to show all resources I need, not a...
Hi eveyone its me again! Im still working on our Master Schedule and this time they required me to put up a Bar Weather Calendar, the specs include MONTHLY ANTICIPATED ADVERSE WEATHER DELAY WORK DAYS, the thing is how will I apply it on the schedule?...
Can we assign / change the default curve on all the resources that are assigned on activities?Like i want to assign a TRAPEZOIDAL curve to all the resources on all the activities.
Hi Guys, Trust you are doing good. I am trying to define a field in P6 and make P6 calculate its value in the future like we can in excel. I know how to define a user field and classify it as a number/start date/integer etc., but is it possible to pu...
how can i create a graph of schedule percentage complete, schedule plan & actual together. I have not added any resources yet nor costs in the project. but say, I have information that out of 100 activities 40 activities have started and out of this ...
Hi guys!can anybody help me where can i download a microsoft project software? i tried some torrent sites but i always got the microsoft office software..any torrent/link/website please? thanks a lot..
Hi -Experts, We got (awarded) one project that is Chemical Plant Project size is small .project duration is 13 Months, Project manager asking me to prepare a L3 schedule while i do not have enough information to do so, information like Procurement , ...
Dear experts. What is the possible mistake done upon having a global change with a program "C" that other program "A" and "B" in other EPS changed also as what in program "C"?. Global change is Rebaseline. Program "C" is a copy of program "B" but d...
I hope I am not putting myself in trouble. I have transferred a productivity book to P6. It's from the KSA Chamber of Commerce dated 2007. I wanna share it but I am thinking I might be putting myself into trouble. It's almost 98% done but I don't hav...