If I run a report to view all my project resource budgeted hours everything shows up. In another report I created to show budgeted hours, earned hours, at completion, and scheduled % complete and then set my filter to show all resources I need, not all the resource hours show up. Looks like those avtivities that have multi resources assigned to them don't add up in the second report. Any suggestions?????
Multi-Resources in Report
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
I ussally export all the data i.e. Resource by Act ID and then use the Pivot tabel to prepare the report. Just trying doing all the sort, filtering in Excel. Thanks.