Multi-Resources in Report

If I run a report to view all my project resource budgeted hours everything shows up. In another report I created to show budgeted hours, earned hours, at completion, and scheduled % complete and then set my filter to show all resources I need, not all the resource hours show up. Looks like those avtivities that have multi resources assigned to them don't add up in the second report. Any suggestions?????

R
Rashid Iqbal 👤 Member for 16 years 2 months

I ussally export all the data i.e. Resource by Act ID and then use the Pivot tabel to prepare the report. Just trying doing all the sort, filtering in Excel. Thanks.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts